|
Irene Rebuild Page Nine 28th June 2006
With nearly all the beams in place it was time to sort out the staple knees. These are horizontal bands of metal shaped as the name implies like staples. They act as spacers between the beams and attach the beams to the futtock ends. Most survived the salvage operation but with few exceptions were bent and distorted. Steve is our metal man - with a big fire, large pincers, an anvil and a sledge hammer with muscles to swing it. The staple irons were reshaped, grit blasting and galvanising followed and they are now in the process of being built into the fabric.
Steve also
made a start on the hanging knees. These are even more weighty chunks
of iron that attach at one end to the underside of the beam and the
other to the inner ceiling, some of them going right down below the
lower deck.
These were cut off at 65ft, a length that we could neither transport by road nor get down the lane to Bagmill Creek - it was an excellent opportunity for a trans-riverine voyage of the fleet. The two logs were effectively delivered to the riverside two miles down river from Gunnislake Bridge.
Meanwhile, the Minnie McLean and the Progress (both Scottish Trawlers) one towing the RIB and the other Irene’s wooden dinghy.
The fleet set off down the Lynher then up the Tamar under the bridges hammering their way up against a falling neap tide. There is virtually no river traffic above Calstock and the stretch of river above Morwelham Quay was as delightfully deserted as it must have been in medieval times.
But the tide drained the water away some half a mile short of where our future masts were waiting to be launched into the river.
There was enough water for the dinghies to make it up to where John Wotton, master tree feller and now an aggressive tractor driver, managed midst roaring engines and spinning tractor wheels to bully the timber into the water.
It was a simple job to tow one down to where the Minnie McLean waited high and dry. The other log was secured on the river bank too high to float. Undeterred the crew took the dinghies up at the 2.00 a.m. High Water and brought the second log down to the waiting trawlers.
With a log bent on each side and the little Progress behind to act as an emergency rudder the fleet started down river avoiding with care the moored yachts and the Calstock viaduct.
The whole operation went very smoothly and we were able to get within three quarters of a mile of Bagmill Creek before the water ran out and the Minnie McLean spent the next few hours waiting for it to come back. Meanwhile the Progress and the RIB were able to take the logs the last stretch and deposit them in the Creek.
The Minnie McLean and the two remaining crew were rescued after midnight. We bumped our way over the bottom in pitch blackness with mud banks a few feet on each side.
It was all
together a good experience. . ..........................................................................................................................................
There is much original wood that we have had to
remove from the ship and we think it possible that people may want to
own a bit of the original timber.
We can supply rough bits, charred bits, big bits and carved
bits – things like name plates, egg cups, coat hangers and coat pegs
with boards bristling with fastenings.
Or you might prefer a block of new Oak.
Soon we will be cutting the ends of the frames down to shear
strake level and that will leave us with a couple of hundred blocks of
6 x 6 of varying lengths. Wood
new or old would be priced at £15.00 a cubic foot (minimum order £5)
plus post and package. Shaped or carved pieces will depend on how much time the
carver has put into the project.
If you have a special idea that you want made by us, we are all
ears.
|