|
Irene
Rebuild
Page
Eleven
4th January
2007
The covering board of a wooden
vessel is at the outer edge of the deck. As its name implies it covers, in
this case, the top of the frames and the beam ends – both with exposed end
grain – open to water & rot. The covering board is there to
protect.

Ted fitting the inner half of the
covering board.
Irene’s original covering boards were made of
sweet chestnut – ‘poor man’s oak’. Over the sixty years of her commercial
life, the Chestnut rotted – rain entered and futtock top and beam end
softened.

Covering board inner half on the port side.
Further astern the outer board is in position.
The rebuild of 1980 was the consequence. This time we are using Opepe– a
tropical hard wood that should do better than the chestnut.

Covering board at the stern.
Before
the hanging knees can be positioned, the inner ceiling had to be
fared. The fairing bug has infected the team – they are now
caulking, paying and fairing her external planking to make her
carressable.

Fairing starboard hull
Work on the first log is nearing completion, but
add-ons await – hounds, crane, mast cap, peak halyard fittings, cross
trees and trestle trees, all to come later.

Shaping complete.
The Gardners have been
delivered. Clean, smart, well painted – an external image which I am sure
represents the same careful attention to detail within. Gear boxes to be
delivered and installation once off the grid.
 
Impressive finish
Props & prop
shafts are out for servicing, the old engine mounts removed, Port A frame
(to hold the outer end of the prop shaft) reseated. Garth, our new
engineer and John are busy measuring and debating on the new engine
mounts.
Steve, the iron man, has finished the hanging knees – now
galvanised and in process of installation. He is now working on repairs of
other iron – mast fittings, dolly winch, mast bands – and where
appropriate, rebuilding in steel.

A hanging knee in the process of of
reshaping.
The deck planks have been
delivered and await the thicknesser and the decision on caulking wedge.
Mast partners and quarter inserts are built.

Mast partners from below. Plywood covers to
protect the unwary.
Meanwhile Syd has been
toiling away in his back garden remaking the ironwork for the windlass –
to 2006 accuracy standards plus Syd’s additional accuracy
factor.

The rocker box to drive the windlass.
The recent 90 mph gale plus a few million litres of rain
water, plus a high tide helped by the Atlantic surge caused a minor
devastation. Clearing the mess has left the site neater and tidier than
anytime since the work started.
.
..........................................................................................................................................
|